Asset report
| |
7 Pages

Marcona (Mina Justa) copper minesite project


Marcona (Mina Justa) copper minesite project

Report summary

The following notes and accompanying analysis consider a combined open-pit SxEw and concentrator operation based on a definitive feasibility study (DFS) completed in June 2009. Oxide ore (12Mt/a) will be vat-leached and processed to copper cathode using SxEw over an 11-year mine life and sulphide ore (5Mt/a) will be milled over a 10-year mine life.

As at October 2013, the project was fully permitted and partially financed however work is still being carried out on a pre-feasibility study.

What's included?

This report includes 2 file(s)

  • Marcona (Mina Justa) copper minesite project PDF - 520.95 KB 7 Pages, 1 Tables, 1 Figures
  • Marcona (Mina Justa) copper minesite project XLS - 508.50 KB

Description

This Copper Metals Mine report provides a detailed analysis of the cost profile, geology, reserves and future production for this mine, as well as a detailed location map.

Copper producers, advisors and financial companies can use this report to better understand asset value and efficiency of the operation. It will also help you benchmark against similar mines, identify acquisition opportunities and examine evolving cost structures to strengthen business strategies.

Wood Mackenzie's cost methodology is the established global industry standard, relied on by the world’s leading investment banks and mining companies to make strategic, operational and investment decisions.

Our analysts are based in the markets they analyse, working with high-quality proprietary cost databases and cost curve analyses to write consistent and reliable insights. Our database includes over 2,450 asset analyses covering more than 1,000 companies worldwide.

  • Key facts
  • Summary and key issues
    • Summary
    • Key issues
  • Location maps
  • Participation
  • Geology
  • Reserves and resources
  • Infrastructure
  • Costs
    • CAPEX
  • Production
  • Operations
    • Mining
    • Processing
      • Leach/ SxEw
      • Mill
  • Sales contracts
    • Off-take agreements
  • Fiscal and regulatory
    • Royalties
  • Timeline

In this report there are 2 tables or charts, including:

  • Key facts
    • Key facts: Table 1
  • Summary and key issues
  • Location maps
    • Detailed map
  • Participation
  • Geology
  • Reserves and resources
  • Infrastructure
  • Costs
  • Production
  • Operations
  • Sales contracts
  • Fiscal and regulatory
  • Timeline
Requester's name : .............
Department : .............
Authoriser's Name : .............
Authoriser's signature : .............
Date : .............
Cost Centre : .............

Questions about this report?

Frequently Asked Questions

Mailenquiries@woodmac.com
  • Europe: +44 131 243 4699
  • Americas: +1 713 470 1900
  • Asia Pacific: +61 2 8224 8898
contact us

Why Wood Mackenzie?

As the trusted source of commercial intelligence for the world's natural resources sector for more than 40 years, we empower clients to make better strategic decisions with objective analysis and advice. Find out more...