Editorial

US utilities are leaving non-wires alternatives on the table

Proposed non-wires alternatives are still often deemed either more expensive or less reliable than the conventional reinforcement option

1 minute read

Our latest research report on non-wires alternatives (NWAs) finds that on average, NWA opportunities proposed in the United States move forward only 40% of the time.

That’s because NWA proposals are still often deemed either more expensive or less reliable than the conventional reinforcement option.

Most identified NWA opportunities are not implemented

We define NWAs as projects in which utilities use distributed energy resources (DERs) and other technologies to reinforce the grid, instead of relying on conventional transmission and distribution assets.

Regulations in some states encourage utilities to identify NWA opportunities whenever possible, but the decision on whether to pursue them is left to utilities’ cost-benefit analyses.

The pipeline of new NWA opportunities — those looming grid upgrades that could potentially be met through DERs, according to the assessment of the utilities that have identified them — is growing in the U.S.

According to our data, NWA projects comprising a total of approximately 850 MW of power capacity in the have been identified or implemented across the country. 

However, these developments have remained too slow-paced and infrequent to elevate NWAs to the level of a significant business opportunity for DER providers.

Most of these projects are in states where regulators mandate that utilities identify new NWA opportunities as part of their grid planning processes, such as New York and California. Indeed, these two states host 72% of the 321 projects included in ours U.S. NWA database.

At the same time, as regulators push more utilities to report on a wider set of potential NWA projects, the proportion of NWA opportunities being implemented compared to the total identified in the database is shrinking. That's because an increasing number of identified projects have little to no hope of moving on to the solicitation stage.

This situation has created a double-edged sword for the sector. On one hand, broad disclosure of NWA opportunities provides useful information for interested third parties, such as DER providers and utilities and regulators in other states.

On the other hand, this broad disclosure dilutes the share of NWA projects progressing toward implementation. This situation risks decreasing interest in NWAs from the same third parties, as projects only move forward in 40 percent of cases.

Cost and reliability concerns are the main factors that result in projects not being pursued.

Every NWA project is unique and presents its own specific challenges. The strength of relationships between DER providers and utilities is a major factor in determining whether NWA projects move forward, as are siting and permitting issues. All of this complicates relying on DERs for grid upgrades, even for those utilities that have openly committed to pursuing NWAs.

Battery storage emerges as preferred NWA resource

Declining DER costs and the development of new value streams for DERs via market design reform will be key enablers of greater penetration of NWAs on the U.S. grid over the coming years.  

For example, we expect that the implementation of FERC Order 841 to increase the feasibility of NWAs that use battery storage solutions.

The ability to value-stack by participating in wholesale markets will likely enable DERs providers to offer utilities a more attractive solution for their NWA projects.

Our H1 2020 report finds that of those NWAs that do move forward, front-of-the-meter battery storage is the technology of choice.

Thanks to its greater cost-competitiveness compared to other resources, battery storage accounts for the majority of NWA project capacity currently under implementation in the U.S., and we expect FERC Order 841 will strengthen this trend going forward.

Asset Report

Grid Edge Insight

SE Mananda (Ceased)

The South East Mananda field is located in the Southern Highlands of Papua New Guinea, 13 kilometres northwest of the Kutubu facility.
Buy this report