Report summary
The Belaya Gora mine is an open pit operation that utilises conventional mining methods. Ore is processed by a gravity concentration circuit. Ore from the nearby Blagodatnoye deposit which is anticipated to be incorporated into the operation will also be mined using conventional open pit mining methods. Processing of ore from Blagodatnoye will require modifications to the processing plant, to include, the addition of a carbon-in-pulp (CIP) circuit. Work commenced on the upgrade of the processing plant in Q4, 2019.
Table of contents
- Summary
- Key issues
- Mining
- Processing
- CAPEX
Tables and charts
This report includes 1 images and tables including:
- Detailed map
What's included
This report contains: