The Lagoa Salgada mine has a 14-year production plan established in the 2023 Definitive Feasibility Study (DFS). The underground mine has a target production rate of 1.2 million tonnes per annum. The mine design utilizes a single access ramp for ore haulage and personnel transport, with the primary mineral treatment plant located on-site to produce concentrates of zinc, copper, lead, and tin, as well as gold and silver doré.