Key Issues
- Development drilling continues at Grane
- Breidablikk ramps up to plateau production
- Licence extension expected
- Decarbonisation - electrification is being considered
- Gas blowdown expected in 2030
- Breidablikk
- Breidablikk (Grane D and F)
- Recovery rate
-
Emissions
- Grane
- Breidablikk
-
Development drilling
- Grane
- Breidablikk
- Historical development activity
-
Capital costs
- Grane
- Breidablikk
- Decommissioning costs
-
Operating costs
- Emissions taxes
- Breidablikk
- Cash flow
- Fiscal terms
- Cash Flow
- Grane cash flow (US$ million)
- Grane cash flow (NKr million)
- 3 more item(s)...
Tables and charts
This report includes the following images and tables:
- Capital Costs 2044 to 2049 (NKr million)
- Cash Flow (US$)
- PV Table (US$)
- Summary Table (US$)
- Split of Revenues
- Cumulative Net Cash Flow - Undiscounted
- Cumulative Net Cash Flow - Discounted at 10% from 01/01/2026
- Remaining Present Value Price Sensitivities
- Cash Flow (Local Currency)
- PV Table (Local Currency)
- Summary Table (Local Currency)
- Cash Flow (US$)
- 25 more item(s)...
What's included
This report contains:
Other reports you may be interested in
Gassled-Oseberg Gas Transport
The Oseberg Gas Transport (OGT) Pipeline links the Oseberg-D gas processing platform with the Heimdal riser platform.
$2,580Grane Oil Pipeline
The Grane Oil Pipeline runs 220 kilometres from the Grane platform to the Sture terminal.
$2,580Skarv Area
The Skarv Area is located between the large Heidrun and Norne fields in the Halten Terrace area of the Norwegian Sea.
$5,280